The Construction Thread

Who checked the shop drawings?

From orlandosentinel.com:


"A 240-ton support girder lies on the ground near a $67 million overpass under construction at the traffic-clogged intersection of state roads 436 and 50 in east Orange County.

The reason: It's about 4 inches longer than it should be.

Construction workers last month discovered the hard way that the beam, which is about 258 feet long and 14 feet wide, was the wrong size.

That's when two large cranes tried unsuccessfully to put it in place in the superstructure of the bridge taking shape over S.R. 436, also known as Semoran Boulevard.

The length essentially was true in the middle, but it was too long toward the outer edges because it's angled, said Armando Perez, project administrator for Cardno TBE, the contracting company overseeing the job for the Florida Department of Transportation.

"Nothing is straight," he said.

Fortunately, there is a simple fix: Workers intend to cut off 2 inches from either end.

They will be relying on numerous consultations between engineers and other construction officials — several of whom could be seen recently inspecting the beam.

Within three weeks, Perez said, the cranes will be used to put the girder back where it belongs.

At that point, it's in "a good storage space," said Perez, who predicted the setback would not affect the planned July completion date.

No cost to taxpayers
Taxpayers, he said, will not have to pay for the mistake. Any extra costs will be borne either by the manufacturer or the design team, he said.

He didn't have a repair estimate."
 
I learned a long time ago not to be afraid to stop everything mid pick and measure. Because they WILL send up shit that is too long and then freak out at you when you can't get it in.

Moral: when making a two-rig, stop-traffic pick, measure first.
 
I learned a long time ago not to be afraid to stop everything mid pick and measure. Because they WILL send up shit that is too long and then freak out at you when you can't get it in.

Moral: when making a two-rig, stop-traffic pick, measure first.

You've talked to my ex's I see.
 
I learned a long time ago not to be afraid to stop everything mid pick and measure. Because they WILL send up shit that is too long and then freak out at you when you can't get it in.

Moral: when making a two-rig, stop-traffic pick, measure first.


I absolutely Hate putting stuff back down again.

If I pick it up, its going in place.
 
I tried to join in and be one of the crew. I even posted a thread about last week's Engineering New Record. All I got was ridiculed and sent to find a 3/8" flat head screw-driver.

All those are in the bucket marked "Bent pry bars".
 
And at 258' long, I think they gotta cut a bit more off. On a hot day, it still won't fit..at least if its steel it won't
 
Back
Top